CEB Cabin Infrastructure 90% Complete
We hope you all had a Merry Christmas and will have a prosperous and Happy New Year!
We have been hard at work during November and December getting all the dirt work and infrastructure complete for the new Compressed Earth Block (CEB) cabin. We’ve trenched and installed the electrical conduit, water line, and septic tank connections. Now we are waiting for our electric company to install the meter and hook up the service side. At that point, we will have all utilities available to the new CEB Cabin. Unfortunately, I had forgotten to install the conduit for the internet. So that is still on the to-do list.
Here are some pictures of the work we have been doing.
Testing Compressed Earth Block (CEB) Production
Compressed Earth Block Cabin Foundation is Complete
Groundbreaking for the Stabilized CEB Cabin
Cabin 3 Teaser
Thank You!
Springtime at Eureka Yurts
Pine View Yurt is Ready!
Raise the ROOF!
Winter has arrived. And with it comes the inevitable construction delays.
After the wall were erected on Yurt 1, it was time to raise the Roof. First step was to calculate the height and positioning of the center compression ring. Once the calculations were complete, checked and rechecked, it was time to construct the stand on which the compression ring would sit. After it was build, Gator and I had to figure out how to get the stand on top of the scaffolding. After a couple failed plans and near drops or falls, we finally succeeded.
Next we had to get the compression ring on top of the 14′ 7″ stand. HUM? For this we had to bring in some additional muscle. Much like the stand, several attempts were made using a pulley system to no avail. So, we decided on trying to build a ramp from the top of the wall to the stand. After a couple hours, the Eagle had landed.
The next task was to secure the roof rafters from the top of the walls to the compression ring. Some slight modifications had to be made to the rafters before we could install. After several hours of tweaking we finally had the first four rafters up. Then came the rain.
We tarped the yurt with a 6 mil 50 x 50 tarp. No easy feat on a rocky slope, I will let you know. We though we had the tarp tight enough to slope the water off the roof, but upon inspection the next day we had huge areas on top of the roof holding massive amounts of water. The tarp grommets had pulled free on several of the tie-downs. So, it looked like we had built an awesome rain water collection system. After several hours I got the water siphoned off the tarp and we reinforced the tie-downs.
Then came the snow. The dogs loved it, the production schedule hated it. I was pressing to try and get the rafters up before the weather set in so we would work inside on the ceiling panels, but it did not happen.
That is the update. Next up is getting the rafters up on Yurt 2, building and installing 80 ceiling sections, wiring the interior, plumbing stubbed out, AC lines installed, and finally having the outer ceiling, interior walls and exterior floor spary foamed with insulation, and metal roofing installed.