Moving Along With Water and Electrical Infrastructure

July 1, 2014 Technical Decisions and Plans  No comments

Update:
So as it stands we have the roads roughed in, 5 sites opened up for a view, Well drilled and state approved.  We have 2 building sites perked and approved by the state.

And on this trip we have gotten approval for the easement for the underground electrical installation, the trenches were dug half the length of the top ridge (1000 ft), junctions put in for potential expansion to the bottom area and the rest of the top ridge, pads built for the transformers for the well house, the first and second cabin.  We also installed all the conduit for the primary run of the electrical and buried it with a 1/4″ rope for use by the electric company to actually pull the electrical wire.

To Do:
1...

Read More