Raise the ROOF!

February 11, 2018 Blog  No comments

Winter has arrived.  And with it comes the inevitable construction delays.

After the wall were erected on Yurt 1, it was time to raise the Roof.  First step was to calculate the height and positioning of the center compression ring.  Once the calculations were complete, checked and rechecked, it was time to construct the stand on which the compression ring would sit.  After it was build, Gator and I had to figure out how to get the stand on top of the scaffolding.  After a couple failed plans and near drops or falls, we finally succeeded. 

Next we had to get the compression ring on top of the 14′ 7″ stand. HUM?  For this we had to bring in some additional muscle.  Much like the stand, several attempts were made using a pulley system to no avail...

Read More